SeaGen Decommissioning Update

Sea Generation Ltd (SGL) will be working on SeaGen from 2nd August, raising the cross beam andpreparing SeaGen for Stage 1 Decommissioning works.Stage 1 decommissioning works are scheduled to be conducted from 6th to 18th August. Stage 1works comprise removal of; crossbeam, lift legs and topside. After Stage 1 decommissioning worksSeaGen will be left as shown in the figure below.SGL continues to work with the decommissioning contractor to conduct Stage 2 decommissioningworks between November 2018 and April 2019 comprising the main cut and lift of the remainingsuperstructure.